Package Replace

Project: Air Handling Unit Replacement
Project Value: $139,592

Background: Intensive Care Unit in a 200 Bed Hospital required replacement of a rooftop HVAC unit on the roof of a 6 story building with a very short duration.

Intent: To complete the job over a 24-hour period.

Project Scope: The equipment had to be replaced in one day to keep temperature control issues to a minimum. It required the use of a very large rane with a long reach, careful coordination with electrical a subcontractor, automatic temperature controls contractor and a roofing contractor.

 The project included the following:

  • Provide design drawings for permits for mechanical electrical and plumbing trades including verifying roof support was adequate for the new unit.
  •  Select equipment that would fit on the existing roof curb as closely as possible and select a new curb adapter.
  • Designate the crane location and crane size as well as the scope of barricading required. o Outlined scope of work and coordinated the efforts of the electrical contractor, temperature control contractor and roofing contractor.
  •  Obtained permits
  • Provide testing and balancing and commissioning once the unit is in.

Results:

  • The project was completed on time and within budget
  • The customer was satisfied with the work completed.